PROJECT IMAGES
Visual placeholder until project photos are supplied by the company.
Kafaa Mining Company Project
Images pending. The artwork shown is a neutral placeholder.
SCOPE OF WORK
Two-stage project: an integrated VAT leaching unit in 2020, followed by a two-vat and Carbon Column expansion in 2021.
Scope of work:
• Stage One (2020): Design and construction of an integrated gold recovery vat using VAT Leaching, including its connection network, all engineering works, and successful trial operation.
• Stage Two — Expansion (2021): An additional expansion comprising the design and construction of two more Processing Vats (2 VATs), design and manufacture of high-efficiency Carbon Columns, and a connection network linking the production lines to increase capacity and improve gold recovery at the site, followed by successful testing of both vats.
Design and construction of a VAT leaching unit followed by a two-vat expansion, Carbon Column manufacture, and trial operation.
PROJECT PHASES
Stage One (2020)
VAT Leaching unit, connection network, and successful trial operation.
Stage Two — Expansion (2021)
Two additional vats, Carbon Columns, a connection network, and successful testing.